Progress Updates As of March 11, 2025
-
Active Construction Projects
Paving Upgrades at West Belmar Elementary School
- Awarded to Catel Inc
- Construction: June 2024 – August 29, 2024
- Construction Update:
- Processing closeout documents
- Work for PCO-3 and PCO-4 Need to be completed.
- Need to Finalize Change Orders
- Catel soliciting pricing for trimming brush near new parking lot.
- Need to Finalize Change Orders
Paving Upgrades at West Belmar Elementary School- Awarded to Catel Inc
- Construction: June 2024 – August 29, 2024
- Construction Update:
- Processing closeout documents
- Need to Finalize Change Orders
- PCO-3: District requested Fence modification and Gate Replacement -$2,940
- PCO-4: Curb work at Entrance -$7,709.63
- Request Price for trimming brush near new parking lot or take credit for Fence Labor?
Interior Alterations at Multiple Schools (Bid 1 – Toilets)- Awarded to Catel Inc.
- Construction Phase 1: June 2024 – August 29, 2024
- Wall High School, West Belmar Elementary School, Wall Primary School
- Construction Phase 2: June 2025 – August 28, 2025
- Allenwood Elementary School, Central Elementary School, Old Mill Elementary School
- Construction Update:
- Punch List items for Phase 1 still need to be completed.
Interior Alterations at Multiple Schools (Bid 2 - WHS and WIS Educational Spaces)- Project Awarded to The Bennett Company
- Phase 1: HS Auditorium and WIS Locker Room Construction: May 1, 2025 to August 29, 2025
- Phase 2: HS and WIS Art/Tech Classrooms: June 16, 2025 to August 29, 2025
- Construction Update:
- Work in Intermediate school Locker Room to commence during Spring Break.
- Balance of work will commence on scheduled dates.
HVAC Upgrades at Allenwood ES, Old Mill ES and West Belmar ES- Project Awarded to Kappa Construction
- Construction: June 2025 – August 2025
- Phase 1: West Belmar Electrical Feeds: Completed
- Phase 2: Boiler Work: June 1, 2025 to September 27, 2025
- Phase 3: Balance of Work: June 16, 2025 to August 29, 2025
- Construction Update:
- Phase 1 work is complete.
- Submittal Review Phase, construction to commence in Summer 2025
HVAC Upgrades at Wall IS, Central ES and Wall High School- Project Awarded to Preferred Mechanical
- Construction: June 2025 – August 2025
- Phase 1: Boiler Work – June 2, 2025 to September 26, 2025
- Phase 2: Balance of Work – June 16, 2025 to August 29, 2025
- Construction Update:
- Permits received on January 2, 2025
- Construction work in all schools is underway – work is primarily hydronic Piping, gas piping, structural steel and
Conduit Installation. - Boiler Abatement at WHS and CES – Pricing received from Preferred was high, district to solicit separate bid for
this work.
Roofing Replacement at Multiple Schools- Project awarded to Pravco Inc.
- Substantial Completion Date: August 30, 2024
- Construction update
- Awaiting final Closeouts
- Partial warranty submission received: Old Mill ES, Wall High School, and Central ES
Projects in Design
Athletic Field Upgrades at Wall High School
- Design/Site Permitting: January to March 2025
- Send to Vendors for Bidding/Pricing: March 2025
- Award: April 2025
- Construction:
- Phase 1: Track Field - Summer 2025 to Fall 2025
- Phase 2: Existing Stadium Field – Fall 2025 to Summer 2026
- Status Update:
- Price Solicitation for Turf Field, Track Surfacing, Bleachers and Stadium Lighting has commenced.
- Pricing for Turf Field and Track Surfacing was received last week and is under review by the district.
- After price solicitation is complete, balance of work (Paving and Stormwater) will be bid publicly to vendors.
- Price Solicitation for Turf Field, Track Surfacing, Bleachers and Stadium Lighting has commenced.
Roofing Replacement at Wall HS and Old Mill ES- Design: July to October 2025
- Bidding: November 2025
- Award: December 2025
- Construction: June 2026 – August 2026