Progress Updates As of March 11, 2025

  • Active Construction Projects

    Paving Upgrades at West Belmar Elementary School

    • Awarded to Catel Inc
    • Construction: June 2024 – August 29, 2024
    • Construction Update:
      • Processing closeout documents
      • Work for PCO-3 and PCO-4 Need to be completed.
        • Need to Finalize Change Orders
          • Catel soliciting pricing for trimming brush near new parking lot.


    Paving Upgrades at West Belmar Elementary School

    • Awarded to Catel Inc
    • Construction: June 2024 – August 29, 2024
    • Construction Update:
      • Processing closeout documents
      • Need to Finalize Change Orders
        • PCO-3: District requested Fence modification and Gate Replacement -$2,940
        • PCO-4: Curb work at Entrance -$7,709.63
        • Request Price for trimming brush near new parking lot or take credit for Fence Labor?


    Interior Alterations at Multiple Schools (Bid 1 – Toilets)

    • Awarded to Catel Inc.
    • Construction Phase 1: June 2024 – August 29, 2024
      • Wall High School, West Belmar Elementary School, Wall Primary School
    • Construction Phase 2: June 2025 – August 28, 2025
      • Allenwood Elementary School, Central Elementary School, Old Mill Elementary School
    • Construction Update:
      • Punch List items for Phase 1 still need to be completed.


    Interior Alterations at Multiple Schools (Bid 2 - WHS and WIS Educational Spaces)

    • Project Awarded to The Bennett Company
    • Phase 1: HS Auditorium and WIS Locker Room Construction: May 1, 2025 to August 29, 2025
    • Phase 2: HS and WIS Art/Tech Classrooms: June 16, 2025 to August 29, 2025
    • Construction Update:
      • Work in Intermediate school Locker Room to commence during Spring Break.
      • Balance of work will commence on scheduled dates.


    HVAC Upgrades at Allenwood ES, Old Mill ES and West Belmar ES

    • Project Awarded to Kappa Construction
    • Construction: June 2025 – August 2025
      • Phase 1: West Belmar Electrical Feeds: Completed
      • Phase 2: Boiler Work: June 1, 2025 to September 27, 2025
      • Phase 3: Balance of Work: June 16, 2025 to August 29, 2025
    • Construction Update:
      • Phase 1 work is complete.
      • Submittal Review Phase, construction to commence in Summer 2025


    HVAC Upgrades at Wall IS, Central ES and Wall High School

    • Project Awarded to Preferred Mechanical
    • Construction: June 2025 – August 2025
      • Phase 1: Boiler Work – June 2, 2025 to September 26, 2025
      • Phase 2: Balance of Work – June 16, 2025 to August 29, 2025
    • Construction Update:
      • Permits received on January 2, 2025
      • Construction work in all schools is underway – work is primarily hydronic Piping, gas piping, structural steel and
        Conduit Installation.
      • Boiler Abatement at WHS and CES – Pricing received from Preferred was high, district to solicit separate bid for
        this work.


    Roofing Replacement at Multiple Schools

    • Project awarded to Pravco Inc.
    • Substantial Completion Date: August 30, 2024
    • Construction update
      • Awaiting final Closeouts
      • Partial warranty submission received: Old Mill ES, Wall High School, and Central ES

     

    Projects in Design

    Athletic Field Upgrades at Wall High School

    • Design/Site Permitting: January to March 2025
    • Send to Vendors for Bidding/Pricing: March 2025
    • Award: April 2025
    • Construction:
      • Phase 1: Track Field - Summer 2025 to Fall 2025
      • Phase 2: Existing Stadium Field – Fall 2025 to Summer 2026
    • Status Update:
      • Price Solicitation for Turf Field, Track Surfacing, Bleachers and Stadium Lighting has commenced.
        • Pricing for Turf Field and Track Surfacing was received last week and is under review by the district.
      • After price solicitation is complete, balance of work (Paving and Stormwater) will be bid publicly to vendors.


    Roofing Replacement at Wall HS and Old Mill ES

    • Design: July to October 2025
    • Bidding: November 2025
    • Award: December 2025
    • Construction: June 2026 – August 2026