- Wall Township Public Schools
- Progress Updates
Progress Updates As of November 5, 2024
-
Paving Upgrades at Allenwood Elementary School
- Awarded to Catel Inc
- Construction: July 2023 – October 27, 2023
- Construction Update:
- Punch List work in progress.
Paving Upgrades at West Belmar Elementary School
- Awarded to Catel Inc
- Construction: June 2024 – August 29, 2024
- Construction Update:
- Close out documents received and in review.
Interior Alterations at Multiple Schools (Bid 1 – Toilets)
- Awarded to Catel Inc.
- Construction Phase 1: June 2024 – August 29, 2024
- Wall High School, West Belmar Elementary School, Wall Primary School
- Construction Phase 2: June 2025 – August 28, 2025
- Allenwood Elementary School, Central Elementary School, Old Mill Elementary School
- Construction Update:
- Punch List issued for Wall High School, West Belmar Elementary School and Wall Primary School.
- Punch List work in progress.
- Window Installation for Wall Primary School to occur over Winter Break or other school holiday.
Interior Alterations at Multiple Schools (Bid 2 - WHS and WIS Educational Spaces)
- Project Awarded to The Bennett Company
- Phase 1: HS Auditorium and WIS Locker Room Construction: May 1, 2025 to August 29, 2025
- Phase 2: HS and WIS Art/Tech Classrooms: June 16, 2025 to August 29, 2025
- Construction Update:
- Contract has been executed and Bonds and Insurance are approved.
- Spiezle issued Notice to Proceed to Bennett on October 23, 2024
- Permit Drawings are completed and ready for pick up by contractor.
HVAC Upgrades at Allenwood ES, Old Mill ES and West Belmar ES
- Project Awarded to Kappa Construction
- Construction: June 2025 – August 2025
- Phase 1: West Belmar Electrical Feeds: July 2024 – In coordination with Catel Inc.
- Phase 2: Boiler Work: June 1, 2025 to September 27, 2025
- Phase 3: Balance of Work: June 16, 2025 to August 29, 2025
- Construction Update:
- Phase 1 work is complete.
- Due to refrigerant phase out units were shipped earlier than anticipated.
- PCO not submitted yet for UV double handling
HVAC Upgrades at Wall IS, Central ES and Wall High School
- Project Awarded to Preferred Mechanical
- Construction: June 2025 – August 2025
- Phase 1: Central School Boilers – June 2, 2025 to September 26, 2025
- Phase 2: Balance of Work – June 16, 2025 to August 29, 2025
- Construction Update:
- Spiezle has received Bonds and Insurance from Preferred, currently in review.
- Once Bonds and Insurance are approved and contract is executed Spiezle shall issued Notice to Proceed.
- Permit Drawings are completed and ready for pick up by contractor.
Roofing Replacement at Multiple Schools
- Project awarded to Pravco Inc.
- Substantial Completion Date: August 30, 2024
- Construction update
- Work is substantially complete and Spiezle has issued punch lists for the work.
- Tremco issued their final punch list items on October 22, 2024.
- Final Punch list verification is tentatively scheduled for the week of November 11
Athletic Field Upgrades at Wall High School
- Bidding: February 2025
- Award: February/March 2025
- Construction: Summer 2025 to Fall 2025
- Status Update:
- FPA to send Spiezle schematic design documents with revised cost estimates on November 8, 2024.
- Spiezle to set up a meeting with FPA and District to discuss revised drawings and cost estimate during the week of November 11.
Roofing Replacement at Wall HS and Old Mill ES
- Design: July to October 2025
- Bidding: November 2025
- Award: December 2025
- Construction: June 2026 – August 2026